This Winter, Every Ride Up Aspen Mountain Starts at Gondola Plaza

Aspen Snowmass is calling 2026-27 its 80th anniversary season. It is also the first winter in decades with no working lift at the end of South Aspen Street, where Aspen skiing began. Lift One went in eighty years ago, and Lift 1A replaced it 55 years ago. SkiCo started taking 1A down in late July, according to Aspen Journalism's reporting on Aspen Public Radio.

Aspen Mountain opens Nov. 26. From that day until a new west-side lift is built, the mountain has one front door at Gondola Plaza. Aspen Journalism describes Gondola Plaza as the ski area's busier base, so funneling everyone through it would be a step backward without the season's other big change. The new Nell Bell chairlift loads at that same plaza. It replaces two old lifts that hardly operated and gives the Silver Queen Gondola a working partner for the first time.

Two Lifts That Barely Ran, Folded Into One

The Nell Bell is a high-speed Leitner-Poma quad. It runs from Gondola Plaza to the top of Bell Mountain and replaces the Little Nell chair, built in 1986, and the Bell Mountain chair, built in 1957, as reported by POWDER. When Aspen City Council approved it in December 2025, SkiCo told The Aspen Times that Little Nell had run only 28 days the season before and Bell Mountain just two.

The Aspen Times approval coverage put the old and new lifts side by side:

Little Nell + Bell Mountain Nell Bell
Installed 1986 and 1957 New for 2026-27
Ride time to top of Bell Mountain 21 minutes combined 8 minutes
Vertical Two separate rides About 2,650 feet in one ride
Planned capacity n/a 1,800 people per hour, per White River National Forest

The Aspen Chamber Resort Association's winter preview, dated Oct. 14, gives the vertical as 2,656 feet. It calls the lift the headline of the season, with "direct access to the top of Bell Mountain from Gondola Plaza." According to The Aspen Times, the top of the Nell Bell connects to the Hero's, Ajax Express and FIS lifts. That makes it a second way into the middle of the mountain, where the old chairs were a slow side route.

The lift has been built quickly. On Sept. 29, POWDER reported that crews were still using a helicopter to fly towers into place. Aspen Snowmass now lists the Nell Bell as "new this season" on its Aspen Mountain page. Check the mountain's lift status before planning an opening-day lap around it.

Why a Lower Lift Matters on Windy Days

A one-base mountain is most exposed when the Silver Queen stops for wind. With 1A running, the west side was a second way up. This winter that backup is the Nell Bell, which sits in the same plaza but runs closer to the ground.

Mak Keeling, Aspen Skiing Company's vice president of mountain planning, explained it to council members in remarks reported by The Aspen Times:

"So we're hoping that that will decrease the wind speeds, so that we can be operating this when the Queen would normally be shut down. But there will, of course, be days that are just too windy for anything."

POWDER described the purpose the same way, citing Forest Service material. The lift is meant to shorten rides, improve how skiers move around the mountain, take pressure off the Silver Queen and offer a way up when the gondola isn't running. Even the ski patrol has moved. The patrol locker room that used to sit at Lift 1A is at Gondola Plaza "for now," according to the Aspen Daily News.

The West Side Still Works as an Exit

Skiers can't ride up from the west side this winter, but they can still ski down to it. The July 31 construction sequencing agreement requires the Aman Aspen crews to keep a ski corridor open past their site for the entire construction period. Keeling told Aspen Journalism that SkiCo intends to keep Schuss Gully open to reach it "as conditions allow." Two nearby runs, Norway and Normandy, are closed.

On a good snow day, a skier staying near South Aspen Street or Dean Street can still finish near home. The next morning starts across town at Gondola Plaza.

What's Happening at the Bottom of the Corridor

The empty lift line is one part of a much bigger construction site. Within the Lift One corridor, the sequencing agreement covers a new Aman Aspen hotel developed by OKO Group, the Chalet Alpina complex of timeshares and residences, the relocation and restoration of the historic Skiers Chalet buildings, and city work on parks and public infrastructure. The Aspen Times reported in early September that Chalet Alpina has broken ground at the historic Lift One base, with completion expected in 2030.

Aspen Journalism's reading of the agreement lays out an estimated sequence. The agreement itself says the schedule is not a binding commitment:

  1. 2026: Both lodging projects could begin shoring and excavation, with Chalet Alpina likely first.
  2. Early 2027: Chalet Alpina begins its subgrade structure, including a parking garage. The Aman building starts taking shape the same year.
  3. 2028: Chalet Alpina's main buildings go up. Aman is enclosed by fall, and SkiCo orders the new lift that fall.
  4. 2029: The lift is installed, and the city's park and infrastructure work is scheduled for the same year.
  5. Winter 2029-30: Estimated ribbon cutting for the new Lift One.

The new lift is planned to reach down to Dean Street, near where the original Lift One loaded. That puts the future west-side base closer to downtown than 1A's ever was. The Skiers Chalet Lodge is also moving down to Dean Street. It will eventually house daytime and seasonal locker rooms, a SkiCo ticket office and the Aspen Historical Society's Aspen Snowsports History Museum at Skiers Chalet. Kelly Murphy, the historical society's president and CEO, told Aspen Journalism that finishing work in late 2029 and opening in early 2030 "seems the most reasonable at the moment."

For neighbors, the more immediate line came from Ben Anderson, the city's community development director, in the same report: "Starting very soon, the entire area will have significant disruption." Under the agreement, the city, SkiCo and both developers meet every two weeks for the length of the project. Both SkiCo and the developers could face steep fees if they cause certain delays that affect the new lift.

The December Weekend That Fills the Plaza

Mid-December stacks several draws onto one weekend. Wintersköl runs Dec. 10 to 13 for its 75th year, with a torchlight descent, fireworks over Aspen Mountain, Soupsköl and, for this anniversary, a drone show. During that same weekend, Aspen Snowmass is selling $80 lift tickets on Saturday, Dec. 12, and Sunday, Dec. 13, to mark the 80th anniversary, according to the Aspen Chamber Resort Association. Aspen Highlands and Buttermilk both open Dec. 12, so the other mountains share some of the discount-weekend crowd.

That weekend also shows how the new setup works under load. Every skier on Aspen Mountain will start in one plaza, with a gondola and a high-speed quad side by side. The trip to the top of Bell Mountain, 21 minutes on the two old chairs, is planned at eight.

If you own near the Lift One corridor, or you're weighing a remodel or purchase along South Aspen or Dean Street during three or more winters of construction, Garrett has spent years on Aspen redevelopment and permitting and can walk through the sequencing schedule with you. Garrett Reuss is glad to talk it over, so book an appointment when it suits you.

Work With Us

We take pride in delivering on the promise of superior service and care for our clients, and have successfully guided hundreds of clients with their sale and purchase of real estate throughout the Aspen/Snowmass area.

Follow Me on Instagram